1. The vibrating feeder is used for dosing, quantitative feeding to ensure uniform and stable feeding and to prevent material flow automatically, the vibrating feeder should be horizontal installed; For general material continuous feeding, it can be installed down-dip 10; For viscous material or material with larger water content ,the vibrating feeder can be installed down-dip 15.
2. After installation, it should leave with 20 mm of interval for vibrating feeder, the suspension device adopts flexible connection.
2. After installation, it should leave with 20 mm of interval for vibrating feeder, the suspension device adopts flexible connection.
3. Before test run, all bolts should be tighten up, especially the anchor bolt of vibration motor, it shall be retightened after continuously operation for 3 to 5 hours .
4. The two vibrating motors must rotate in reverse during test run, if there is any abnormal phenomenon, please stop immediately and solve the problem.
5. During operating, the amplitude, current of vibration motor and surface temperature of motor should be regularly checked . The front and back amplitude must be uniform and no side shaking, the current of vibrating motor should be stable, if there is any abnormal phenomenon, please stop immediately and solve the problem.
4. The two vibrating motors must rotate in reverse during test run, if there is any abnormal phenomenon, please stop immediately and solve the problem.
5. During operating, the amplitude, current of vibration motor and surface temperature of motor should be regularly checked . The front and back amplitude must be uniform and no side shaking, the current of vibrating motor should be stable, if there is any abnormal phenomenon, please stop immediately and solve the problem.
6. The lubrication of vibration motor bearing is the key point for the normal operation of the whole feeding machine. The second-rate molybdenum 2 # grease should be refilled periodically on the bearing, normally fill the grease every two months, and fill once a month during the high temperature season. The motor should be repaired every six months to change the internal bearing.
Please do not hesitate to contact us if you have any inquires, we are ready to serve you better.
__________________________________________________________________________
Henan Pingyuan Mining Machinery Co., Ltd
Address: 289 Yellow River Road, Xinxing City, Henan Province, China.
Tel: +86 373 579 9198
Fax: +86 373 507 1699
没有评论:
发表评论